P6 8.2 - Revised baseline - Copying actuals from status update

Member for

17 years 4 months

Hi Haroon,

I believe the revised logic, duration changes etc will be done on the " in progress / not started" activities. So it will be easy to do these changes in the current schedule, which already have the as built as of now.

After this you can set this schedule as the revised baseline. Is it logic to make the plan for the completed activities, unless it is for any delay claim analysis.

Regards

Kannan

Member for

16 years 3 months

is the schedule has been maintained and assigned the you can go to Project Maintain baseline and select update then check the update activites areleady in the baseline then select the update options and choose what you want updated in the baseline. If you choose the General activity information box this will update each activity in the baseline. The data that wil be updated is activity name, activity type, duration type, percent complete type, status, calendar, and primary resource.

 

if you check Dates, duration, and data date: This udate the Original Duration, Remaining Duration, Actual start/finish, Anticipated start/finish, Remaining start/finish, Start/finish, Early start/finish, Remaining late start/finish, Late start/finish, Suspend/resume dates and Data Dates as well.