yes you can put the steel up and then do the slab depending on what the columns sit on. This will obviously hold off all trades until the steel is set since no one can be working under the steel while it is going up.
It is harder to do underground in the slab area AFTER the steel is up due to the columns being in the way.
I would look at the geographical location of the project and look at the time of year that the roof planned to go in then consider the weather conditions and decide if it is bestto get the projetc under roof ASAP.
As far as the design you wil have
civil or Undergound and site design
structural
electrical
mechanical
architectural
lead times will be for your steel and glazing of the large panes of glass
Member for
16 years 3 monthsyes you can put the steel up
yes you can put the steel up and then do the slab depending on what the columns sit on. This will obviously hold off all trades until the steel is set since no one can be working under the steel while it is going up.
It is harder to do underground in the slab area AFTER the steel is up due to the columns being in the way.
I would look at the geographical location of the project and look at the time of year that the roof planned to go in then consider the weather conditions and decide if it is bestto get the projetc under roof ASAP.
As far as the design you wil have
civil or Undergound and site design
structural
electrical
mechanical
architectural
lead times will be for your steel and glazing of the large panes of glass
Member for
19 years 10 monthsHi ZoltanA comprehensive
Hi Zoltan
A comprehensive list.
What about design and lead times for procurement.
Sometimes it is quicker to get the steel up and then do the slab.
Best regards
Mike Testro
Member for
16 years 3 monthsoptain all permitsidentify
optain all permits
identify any existing utilities
relocate and existing utilities
rough grade site
install underground utilities conduit ductbanks etc
form, rebar, pour slab on grade
Erect steel structure
install building skin
install roofing
interior finishes
look at RS Means or similar estimating software and books for durations based on quantity and or square footage