Planning, Scheduling & Programming Discussion Member for 11 years 3 months Member for 11 years 3 months Submitted by @gary5edwards on Wed, 2014-07-09 18:01 Permalink Thank you very much Dieter. Thank you very much Dieter. Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Wed, 2014-07-09 12:15 Permalink Hi Gary First you must P6 let Hi Gary First you must P6 let calculate them: F9 --> "Options" --> "Advanced" --> mark it plus the number you want. Then you can group and filter by the paths and give them different colours in the bar chart. Good luck with your planning! Dieter Log in or register to post comments
Member for 11 years 3 months Member for 11 years 3 months Submitted by @gary5edwards on Wed, 2014-07-09 18:01 Permalink Thank you very much Dieter. Thank you very much Dieter.
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Wed, 2014-07-09 12:15 Permalink Hi Gary First you must P6 let Hi Gary First you must P6 let calculate them: F9 --> "Options" --> "Advanced" --> mark it plus the number you want. Then you can group and filter by the paths and give them different colours in the bar chart. Good luck with your planning! Dieter
Member for
11 years 3 monthsThank you very much Dieter.
Thank you very much Dieter.
Member for
18 years 9 monthsHi Gary First you must P6 let
Hi Gary
First you must P6 let calculate them: F9 --> "Options" --> "Advanced" --> mark it plus the number you want.
Then you can group and filter by the paths and give them different colours in the bar chart.
Good luck with your planning!
Dieter