PRIMAVERA v6.7 Completing Tasks When Performing Updates with Data Line

Member for

16 years 7 months

When you say activities that "should still be in progress", what do you mean?

 

The update progress option tells Primavera to apply progress to all selected activities as if progress between the previous and new data dates has happened precisely according to the current plan.

 

So long as you have hit F9 before you use the update progress function, none of the dates should change.

 

Personally I think the whole idea of using update progress is dangerous. -I have never worked on a project where everything has gone precisely to plan from one update to the next.

 

(Also: please only hit the save button once when making a post, to avoid creating duplicates)