Graph

Member for

12 years

I can only enter schedule % complete data upto current data date.But i want to have schedule % complete of the whole project before hand.

Member for

12 years

Thanks Mike.I want to show schedule % Complete(the problem is that i dont know how it is giving weightages to the activity and then to whole WBS) with Performance % complete Graph.(This is generated by the work i have done)

Member for

19 years 10 months

Hi Ammar

This kind of data is best generated on an Excell Graph.

Copy the percent complete numbers into an excell sheet from both the actual and target and use the data to present a vertical bar graph for each section of work.

Keep the graph format for the next progress update.

Best regards

Mike Testro

Member for

12 years

Told them to do so but they want progress in terms of duration.

How much performance % is completed of Planned %

Member for

15 years 11 months

Show the Planned Value Cost and Earned Value Cost Curves.

Member for

12 years

Or you can say i want to track my project graphicaly