Thanks Mike.I want to show schedule % Complete(the problem is that i dont know how it is giving weightages to the activity and then to whole WBS) with Performance % complete Graph.(This is generated by the work i have done)
This kind of data is best generated on an Excell Graph.
Copy the percent complete numbers into an excell sheet from both the actual and target and use the data to present a vertical bar graph for each section of work.
Keep the graph format for the next progress update.
Member for
12 yearsI can only enter schedule %
I can only enter schedule % complete data upto current data date.But i want to have schedule % complete of the whole project before hand.
Member for
12 yearsThanks Mike.I want to show
Thanks Mike.I want to show schedule % Complete(the problem is that i dont know how it is giving weightages to the activity and then to whole WBS) with Performance % complete Graph.(This is generated by the work i have done)
Member for
19 years 10 monthsHi AmmarThis kind of data is
Hi Ammar
This kind of data is best generated on an Excell Graph.
Copy the percent complete numbers into an excell sheet from both the actual and target and use the data to present a vertical bar graph for each section of work.
Keep the graph format for the next progress update.
Best regards
Mike Testro
Member for
12 yearsTold them to do so but they
Told them to do so but they want progress in terms of duration.
How much performance % is completed of Planned %
Member for
15 years 11 monthsShow the Planned Value Cost
Show the Planned Value Cost and Earned Value Cost Curves.
Member for
12 yearsOr you can say i want to
Or you can say i want to track my project graphicaly