Change Nonlabour to Labor in P6

1 reply [Last post]
Francis Dominic
User offline. Last seen 6 years 28 weeks ago. Offline
Joined: 26 Mar 2012
Posts: 4
Groups: GPC Qatar

Hi all,

Is it possible to change assigned nonlabor to labor with the help of global change / or any other way?

Dominic

Replies

Abilash Palakkada...
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47

You can use global change or resource replacement options, it your resource assignment doesn't have actual values. Otherwise you will have to remove the actual values by keep the record somewhere else and then replace the resource with new one then put the actual as before.