Planning, Scheduling & Programming Discussion Member for 14 years 11 months Member for 14 years 11 months Submitted by sb_sunil2000 on Tue, 2013-03-19 22:09 Permalink Hi Mike,Thanks a lot for your Hi Mike, Thanks a lot for your valuable reply. In case of SIPS piling method what productivity rate are we following? ,Thanks in advance for your reply.. Best Regards, Sunil. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2013-03-19 09:54 Permalink Hi Sunil Piling will probably Hi Sunil Piling will probably be done from an ofshore barge. If so then you have to consider: State of the tide Wave configuration Weather - monsoon Support and supply tenders When piling is in progress the rest of the work can follow for the jetty deck and top beams. After that you will have normal access. Best regards Mike Testro Log in or register to post comments
Member for 14 years 11 months Member for 14 years 11 months Submitted by sb_sunil2000 on Tue, 2013-03-19 22:09 Permalink Hi Mike,Thanks a lot for your Hi Mike, Thanks a lot for your valuable reply. In case of SIPS piling method what productivity rate are we following? ,Thanks in advance for your reply.. Best Regards, Sunil.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2013-03-19 09:54 Permalink Hi Sunil Piling will probably Hi Sunil Piling will probably be done from an ofshore barge. If so then you have to consider: State of the tide Wave configuration Weather - monsoon Support and supply tenders When piling is in progress the rest of the work can follow for the jetty deck and top beams. After that you will have normal access. Best regards Mike Testro
Member for
14 years 11 monthsHi Mike,Thanks a lot for your
Hi Mike,
Thanks a lot for your valuable reply. In case of SIPS piling method what productivity
rate are we following? ,Thanks in advance for your reply..
Best Regards,
Sunil.
Member for
19 years 10 monthsHi Sunil Piling will probably
Hi Sunil
Piling will probably be done from an ofshore barge.
If so then you have to consider:
State of the tide
Wave configuration
Weather - monsoon
Support and supply tenders
When piling is in progress the rest of the work can follow for the jetty deck and top beams.
After that you will have normal access.
Best regards
Mike Testro