Ship impact protection system

Member for

14 years 11 months

Hi Mike,

Thanks a lot for your valuable reply. In case of SIPS piling method what productivity

rate are we following? ,Thanks in advance for your reply..

Best Regards,

Sunil.

Member for

19 years 10 months

Hi Sunil

Piling will probably be done from an ofshore barge.

If so then you have to consider:

State of the tide

Wave configuration

Weather - monsoon

Support and supply tenders

When piling is in progress the rest of the work can follow for the jetty deck and top beams.

After that you will have normal access.

Best regards

Mike Testro