Problem with baseline incluing actual date

1 reply [Last post]
Amir Mina
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 9 Jul 2007
Posts: 4
Groups: None

Dear All,

Plz help

I've a baseline schedule with some actual dates and duatation % complete. but when i assigned the same to updated prgramme the BL start and BL finsh dates are not the same i assigned ..............

Regards,

Amir

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Assuming you are using Primavera?

 

This sounds like the classic issue of planned dates vs actual.

 

Paul Harris has done an excellent presentation explaining how this works:

http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf