Vico Control2009SP3 resource graph behavior

Member for

14 years 7 months

I made a simple test:move Laborer resources from week1 to week 2; current 18 laborers

      * in control mode

      * move 5 days SWEEP fiberroll

      * move 3 days sweep silt

      * change to design mode

      * refresh and reforecast

      * change back to control mode

The result: still 18 laborers but it looks like something changed

Conclusion: I will test more