EVA terminology - useful info

Member for

20 years 7 months

Tom,

You might want to add:

 

Critical ratio EAC (SPI X CPI)

Cost EAC = BAC / (SPI X CPI)

If BAC = $1M, SPI = .90 and CPI = .80, CR  = (.90 X .80) = .72.

Thus, Cost EAC = $1M / .72 = $1,388,889

 

This formula takes into account that, if you are both over budget and behind schedule, you'll be overspending (indirect costs, LOEs etc.) for longer than planned.  There is much empirical data to show that this is the most accurate EV predictor of Cost EAC.

Fraternally in project management,

Steve the Bajan