Baseline a project, update a project question

Member for

14 years 4 months

Thanks Mike, thats what i have been doing....

I have set the new baseline every time a new activity is introduced.

So would you class changing the resource names of a person working on an activity as a reason to baseline again?

 

cheers John

Member for

21 years 7 months

Not all "baselines" are created equal.

Some are contractual baselines others are not.

Usually a contractual baseline is based from a most probable version of the job and must be approved before it is shown as a contractual baseline in your reports. For contractual baselines follow Mike's advice. The most probable version include buffers at times embedded within the duration of an activity, at other times within artificial non-work hours or days, like artificial holidays, at other times as an explicit buffer activity. Intermediate buffers distort short term schedule and a final single buffer should be reduced as progress happens based on some reduction rule.

On the other hand the use of baselines to display optimistic schedule, to get rid of buffers that artificially "delay" your schedule and to target for optimistic dates in the hope of meeting the contractual dates can be very useful. Just label this baseline as "optimistic target" and use it for your short term projections with no buffers and to manage your job.

The drawback is that it requires you to synchronize two schedules, optimistic updates and contractual updates, a piece of cake in software capable of doing so at a single click of the mouse, an issue in less capable software.

Member for

14 years 4 months

Hi,

I am Faiz.have been working for last two years as Planning Engineer Using Primavera V6.

I needed to ask that when I want show a activity on hold how to show it precisely.I tell you my procedure and you tell me that wither it is right or not??

I have an activity named "Mobilization"

The Planned Start is was 11th june 2011..and it started on the planned date i.e, 11th june 2011,

But it was holded due to some reason on 15th june and will remain holded till 18th june.

So I Started the activity..then entered the date of suspension and also the date of resumption.

is it Right??????But in bar chart it delays the activity not showing any different color for the suspended period...how to show it in the bar chart or activity table???

 

regards,

Member for

19 years 10 months

Hi John

The general rule is that you do not change the approved baseline until another baseline is approved - only monitor prigress on the approved baseline.

Save the baseline in a new file for any adjustments and when that is approved call it Baseline R1 or something similar and then continue monitoring progress on that.

Repeat the procedure whenever changes arise.

Best regards

Mike T.