Improved Planned Completion Date - NEC

Member for

16 years 7 months

Tony,

Assuming the programme was rejected for one of the 4 reasons specified in the contract (cl 31.3), and within 2 weeks of submission, then yes you are both obliged to assess the impact of the additional works vs the latest accepted programme.

 

Cheers,

 

G