Planning, Scheduling & Programming Discussion Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Wed, 2011-06-15 22:33 Permalink Tony, Assuming the programme Tony, Assuming the programme was rejected for one of the 4 reasons specified in the contract (cl 31.3), and within 2 weeks of submission, then yes you are both obliged to assess the impact of the additional works vs the latest accepted programme. Cheers, G Log in or register to post comments
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Wed, 2011-06-15 22:33 Permalink Tony, Assuming the programme Tony, Assuming the programme was rejected for one of the 4 reasons specified in the contract (cl 31.3), and within 2 weeks of submission, then yes you are both obliged to assess the impact of the additional works vs the latest accepted programme. Cheers, G
Member for
16 years 7 monthsTony, Assuming the programme
Tony,
Assuming the programme was rejected for one of the 4 reasons specified in the contract (cl 31.3), and within 2 weeks of submission, then yes you are both obliged to assess the impact of the additional works vs the latest accepted programme.
Cheers,
G