Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS for EPC project (engineering-procurement-contstruction)

6 replies [Last post]
Alessandro Gebbia
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 27 Dec 2010
Posts: 23
Groups: None

Hello friends, I have been asked to develop an EPC work-breakdown. I just completed the construction wbs but i have no ideas about E and P, I am too new in this field. Would you please suggest me an example or an already made structure so I can start working on it and adequate it to my needs?

 

Thank you very much

Replies

Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Ideally, you should never develop WBS on your own. It should always be a team effort corresponding to concerned disciplines or specialties. Like for example: You were asked to develop a process flow diagram when you were never a process engineer. So how could you be able to do that? However, reality in construction projects is so difficult to understand or managed. And just ultimately resulting to whatever they can just do best and fast (even copying other works that were totally different from what they intend to do), only to satisfy some stupid contract requirements or not defaulting the contract. So still wondering why most construction projects (if not all) fail? Or always spending beyond budget and always late?
dhon bartolome
User offline. Last seen 36 weeks 2 days ago. Offline

hi,

Simple WBS

Enggineering 

    > Submissions (Drwgs) 

    > Review and Approval (Drwgs)

Procurement 

   > Submissions (Material/Technical) 

   > Review and Approval (Material/Technical) 

   > P.O 

   > Fabrication/Manufacturing Cycle 

   > Onsite Deliveries 

masoud sedaghat
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 26 Jan 2016
Posts: 2
Groups: None

Hi . I Need WBS for EPC Project

Dinesh Kumar
User offline. Last seen 4 years 28 weeks ago. Offline
Joined: 8 May 2006
Posts: 29

A raw example (curtailed version) of a typical FPSO project WBS may look like

 

PHASES

                Milestones,Management

                Engg, Proc,  Const

WORK PACKAGES

                Vessel

                Topsides & Process

                Turret & Mooring

                Subsea system etc

AREA/MODULES

                Gas Compression

                Polishing

                K O Drum

              Power Generation / LocEqpRm

                Utilities

                Helideck

DISCIPLINES

                SMP E&I              

MISC

 

Project Name

  1. Milestone

  2. Project Management

  3. Statuary Approvals

  4. ENGINEERING

    1. client deliverables

    2. Detailed dwg development & Approvals

    3. QC documents

  5. PROCUREMENT

  6. CONSTRUCTION

  7. Completion & COMMISSIONING

  8. Load-out / Handover

Evaristus Ujam
User offline. Last seen 11 years 38 weeks ago. Offline

Just for the sake of emphasis,  your WBS  for engineering and procurement  in a typical  Oil and gas environment may  look like this:

(1) Process, Mechanical, E & I Design

(2) Location (pipe racks, Flare, inlet manifolds, utility area,etc)

(3) Work items (pipes, KOD, Tank, heaters Pumps, valves, etc)

(4) Deliverables(P&IDs, Plot plans, Isometrics, etc)

 

Procurement

(1)Discipline ( Civil/structural, M&E, Instrument)

(2) categories ( local, Foreign)

(3) Shipment (Discuss methology & procurement sequence with experts in procurement Dept)

(4) Work item (equipment, valves, pumps, specialists of diff trades).

Note that process leads in engineering while  Civil structural activities take precedence in most construction activities.

 

Regards

Ujam

 

 

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

wbs = work breakdown structure. the clue is in the name. How do your engineering & procurement departments breakdown their work?

 

They might break it down like the following example, they might not. Speak to them to find out

 

1) Engineering

2) Discipline (civ, mech, elec, etc)

3) Sub-discipline (groundworks, paving, buildings, etc)

4) Area / workfront / whatever you call it

5) Deliverable type (calcs, drawing, survey, etc)

 

1) Procurement

2) Discipline

3) Procurement Item (rebar, piling contractor, etc)