hi Shazia, Just for share the knowledge, as I just arrived to this forum ...
Yes Daniel is right, they all pipes, but to increase our knowledge and just want to share what I've learn from the course
(If you are an engineer don't hesitate to ask your manager for getting more training in Engineering, to have training such as Piping and pipeline design etc, would increase your skills for planning)
Piping Terminology;
Transmition pipelines: Usually long, relatively large diameter lines, May Tranport Hydrocarbon fluids and or Gas. from prudocing fields to processing plant or refineries.. From plants and refiniries to marketing centers
Flowline: Two phase lines (Non separted HC with two phase (liquid and gas) flows before entering the inlet separator), connecting welss to production manifolds. range from 2 - 20 inches.
Trunkline: Two or more well flowlines connected to a larger line that carries the combined well stream to the production manifold. range from 10 to 42 inches.
Injection lines: Transport high pressure gas or water to wellheads for injection into the producing formation. Fluids are injected for: Reservoir pressure performance, production enhancements, conservation of gas, Gas Lift, Produced water disposal , waterflood, steam flood.
Piping / Plant (Facility) Piping (on plot) : Piping witihin the well defined boundaries of the processing plants, piping compression station or pumping station. Used for a variety of fluids within those boundaries as required.
Warmest regards from Indonesia
Alex Iskandar, PMP
Member for
24 years
Member for24 years
Submitted by Daniel Limson on Thu, 2010-09-16 09:23
I do not see any difference at all, they are all pipes to me.
As a planner, what you need to know is basically the diameter of the pipe, the lenght of the pipeline and your welding production rates. You also need to know whether it is above ground or underground. If it is underground you need to know the soil conditions, where the pipe is being laid. If it is above ground you need to construct pipe sleepers to protect the pipe. You need to look at the scope of work. Does it require cathodic protection? Does it require insulaton or painting?
If the pipeline is for Gas or Oil you may need to know about cold cutting and tie-in procedures.
Member for
17 years 6 monthsAlex, Thanks for your
Alex,
Thanks for your explanation this is rely what i was looking for,
construction Sequence. (please correct me if i am wrong)
Piping- Fabrication
Pipe sand Blasting painting
Marking and Bevel cutting.
Welding
NDT
Hydrotes (spool testing.)
Installation if Ground piping if,
Erection.
Erection on the Pipe rack
Welding erected spool pipe
NDT
Hydro test
Chemical cleaning / passivation.
Insulation
or final coat paint.
Pipeline:
Stringing of the pipe (on trench Side)
Welding
NDT
wrapping Coating or insulation of pipe Joint
Lower the pipe in the trench
Back filling of Trenched
Pig Cleaning
Ready for operation.
Please advise me if this correct sequencing.
Member for
21 years 9 monthsPiping and Pipeline Terminology
hi Shazia, Just for share the knowledge, as I just arrived to this forum ...
Yes Daniel is right, they all pipes, but to increase our knowledge and just want to share what I've learn from the course
(If you are an engineer don't hesitate to ask your manager for getting more training in Engineering, to have training such as Piping and pipeline design etc, would increase your skills for planning)
Piping Terminology;
Warmest regards from Indonesia
Alex Iskandar, PMP
Member for
24 yearsDifference between Piping and pipeline, what is Pipeline project
Shaza Khan,
I do not see any difference at all, they are all pipes to me.
As a planner, what you need to know is basically the diameter of the pipe, the lenght of the pipeline and your welding production rates. You also need to know whether it is above ground or underground. If it is underground you need to know the soil conditions, where the pipe is being laid. If it is above ground you need to construct pipe sleepers to protect the pipe. You need to look at the scope of work. Does it require cathodic protection? Does it require insulaton or painting?
If the pipeline is for Gas or Oil you may need to know about cold cutting and tie-in procedures.
Best regards,
Daniel