Dates Constraints

7 replies [Last post]
Naga Bhushan Reddy
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 29 Apr 2010
Posts: 12
Groups: None
Can any one guide me as to how to change the start and mush finish dates for an schedule also which is updated

Replies

Naga Bhushan Reddy
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 29 Apr 2010
Posts: 12
Groups: None
ok thanks Mr.Rodel
Naga Bhushan Reddy
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 29 Apr 2010
Posts: 12
Groups: None
ok thanks
Rodel Marasigan
User offline. Last seen 17 hours 3 sec ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Bhushan,
Project finish date is not editable. It is the result of logic assigned to activities. You can forced finish date by adding mandatory finish constraint on the last activity but it will gave you wrong float calculation and not advisable.
Naga Bhushan Reddy
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 29 Apr 2010
Posts: 12
Groups: None
Thanks , also can a project finish date can be removed for must finish date
Rodel Marasigan
User offline. Last seen 17 hours 3 sec ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Bhushan,
Your thread title is Dates Constrains and that how I interpret it. Maybe you are looking for Project Window detail-> Date Tab and under Schedule dates change Project Planned Start & Must Finish date.
Naga Bhushan Reddy
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 29 Apr 2010
Posts: 12
Groups: None
I mean how to change project start dates and finish dates for project

Bhushan
Rodel Marasigan
User offline. Last seen 17 hours 3 sec ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Naga Bhushan Jangam,
Activity Window Detail-> Status tab. You should find Constraints section: Primary and Secondary and change the constrain type that you wanted.