Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to set Baseline- After revised the Schedule and to

4 replies [Last post]
abbas india
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
Hi all,,

Can anybody know how to set baseline after we revised the Schedule and to set this revised Schedule as a baseline to the revised current schedule.??


When I tried by Project - Maintain baselines- add- save a copy of the revised schedule and assigned to the revised current schedule, it gave me wrong baseline dates and all completed activities having without Actual dates in it.

Please help,

Best regards,
Abbas

Replies

Iyke Nwosu
User offline. Last seen 5 years 13 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 6
Groups: None

Dear Abbas,

when you want to maintain your baseline, selecting "Save a copy of the current project as baseline" will maintain the baseline based on that very project, to correctly select the right baseline, choose the second option "Convert another program.........", make sure to have imported the baseline program and select the program, Assigne afterwards. Re-schedule and your actual dqate will return.

 

Regards

Iyke Nwosu

Ferdinand U.
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
abbas india
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35
During revision itself we will have actual dates in i!!

The same file is taking a copy and assigning as baseline but it loosing the actual dates.

Abbas
Ferdinand U.
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
you need to use global change for activity status equals in progress and completed before assigning as baseline