when you want to maintain your baseline, selecting "Save a copy of the current project as baseline" will maintain the baseline based on that very project, to correctly select the right baseline, choose the second option "Convert another program.........", make sure to have imported the baseline program and select the program, Assigne afterwards. Re-schedule and your actual dqate will return.
Regards
Iyke Nwosu
Member for
18 years 3 months
Member for18 years3 months
Submitted by Ferdinand U. on Sat, 2010-04-03 12:03
Member for
8 years 4 monthsDear Abbas,when you want to
Dear Abbas,
when you want to maintain your baseline, selecting "Save a copy of the current project as baseline" will maintain the baseline based on that very project, to correctly select the right baseline, choose the second option "Convert another program.........", make sure to have imported the baseline program and select the program, Assigne afterwards. Re-schedule and your actual dqate will return.
Regards
Iyke Nwosu
Member for
18 years 3 monthsRE: How to set Baseline- After revised the Schedule and to
http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=8&Top=50178
Member for
16 years 3 monthsRE: How to set Baseline- After revised the Schedule and to
During revision itself we will have actual dates in i!!
The same file is taking a copy and assigning as baseline but it loosing the actual dates.
Abbas
Member for
18 years 3 monthsRE: How to set Baseline- After revised the Schedule and to
you need to use global change for activity status equals in progress and completed before assigning as baseline