Early and late S curves in P5.....

1 reply [Last post]
Martyn Coates
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 8 Aug 2007
Posts: 32
I seem to be having a problem getting the curves from p5

I want the data in excel and want to show early and late curves like you can do in P3 for a project.

There seems to be remaining setting dates etc but I can not see any setting to give the whole hour spread from start to finish (whether actual or not) in the form of an early & late curve.

help

I havent seen any definative guide or help to anyone else in older posts

Replies

Nathaniel Alexander
User offline. Last seen 13 years 47 weeks ago. Offline
Joined: 5 Jun 2003
Posts: 9
Martyn

Try the following

1)Report Wizard select Time Distribution Data Box
2)Choose the report - Activity Resource & role assignments
3) Select options
4)Filter as follows - Where Open Status = open
5) go to Time interval Fields and select
--Remaining units - remaining early
--Remaining Late units - Remaining late
then next next till the report finishes

Hopefully this will do the trick