Planning, Scheduling & Programming Discussion RE: Early and late S curves in P5..... Martyn Try the following 1)Report Wizard select Time Distribution Data Box 2)Choose the report - Activity Resource & role assignments 3) Select options 4)Filter as follows - Where Open Status = open 5) go to Time interval Fields and select --Remaining units - remaining early --Remaining Late units - Remaining late then next next till the report finishes Hopefully this will do the trick Log in or register to post comments
RE: Early and late S curves in P5..... Martyn Try the following 1)Report Wizard select Time Distribution Data Box 2)Choose the report - Activity Resource & role assignments 3) Select options 4)Filter as follows - Where Open Status = open 5) go to Time interval Fields and select --Remaining units - remaining early --Remaining Late units - Remaining late then next next till the report finishes Hopefully this will do the trick
RE: Early and late S curves in P5.....
Martyn
Try the following
1)Report Wizard select Time Distribution Data Box
2)Choose the report - Activity Resource & role assignments
3) Select options
4)Filter as follows - Where Open Status = open
5) go to Time interval Fields and select
--Remaining units - remaining early
--Remaining Late units - Remaining late
then next next till the report finishes
Hopefully this will do the trick