Programme Level Types
Hi All
From time to time I come across phrases like Level 5 Type programme, Level 3 Type Programme etc. I am assuming this refers to the level of detail contained within each programme type. Can anyone please advise me as to what level of detail is required for each programme level type? I have heard a few conflicting explanations, does anyone have a definitive answer.
Thanks for your help
John
My understanding from reading a delay and disruption book that there are mainly 5 levels of programmes.
Level 1 - Master Programme in general Summary programme
Level 3 - Construction Programme is what I start at for building programmes.
Level 4 more detailed than L.3
Possibly L.5 a daily programme
If there is a L.6 this could be a hourly prog
Hi Mike
I know I am a bit late but PEO has gone BANG
Paid my membership fee last year, not updated on their web site members page
Phoned / emailed - no replys no refund
then read the article by Gary France
In my experience, it seems that many people have a misconstrude idea as to program levels.
Generally, you need to comply to your contractual obligations. Generally, an NEC based contract will require a level 4 schedule, which will be a system and sub-system based program, and FIDIC requires normally a level 3 reporting schedule, highlighting mainly your systems.
The setup I have used over the years which has sufficed every client I have worked with on a contract for both external and internal reporting purposes is as follows.
Based on a WBS level that can correlate back to either your BOQ and or DOW, whichever your company utilises.
WBS Level 0 - Project
WBS Level 1 - Project Phases
WBS Level 2 - Discipline
WBS Level 3 - System or Area
WBS Level 4 - Sub-System
WBS Level 5 - Scope (Origional, additional[to indicate delay])
If anyone wants more detail on this, as its a great method, please mail me...
John,
You shall decide based on your own needs what each level means, the same goes for your clients. Different job types might require more or less levels, creating an all inclusive generic level definition might be too much, and this applies for your different Portfolios.
It is pretentious and technically wrong for others to force you to exclusively use their definition because theirs is better than yours as if the exclusive owners of all truth.
The solution is simple, maintain your jobs as per your own company standards and create a WBS for this purposes, then create additional WBS for the needs of your clients. If your software do not provide for multiple WBS I suggest you dump the “trompo toy” and get serious software.
I keep a WBS based on Area at a higher level and Function at a lower level, a WBS based on Function at a higher level and Area at a lower level, at rare times I keep an additional based on responsibility and of course, another for whatever the Client asks.
What if your Portfolio which include other jobs by other clients/owners is based on several WBS none of which is compatible with the caprices of a particular client/owner. Calling for a single WBS functionality got to be called by its name “is stupid”.
Regards,
Rafael
Contrary to some of the comments below, there is a remarkable degree of consistency among professional planners and organisations in the meaning allocated to different levels. A detailed analysis of the 5 levels can be downloaded from http://www.mosaicprojects.com.au/Planning.html#Roles
We have had this disussion before.
I do not promote FS links with bottom up planning because I am adelay analyst but because it is the simplest and best manner of putting together a programme.
I have also said that if you cant build it you cannot plan it.
Top down FF SS on global bars has - at some time - to be developed into a level 4 from 1 2 & 3.
When that happens the results will be different and then the temptation is there to squeeze or stretch the L4 tasks to fit.
It all makes work for me.
Best regards
Mike Testro.
Programme level type for me is vital. Mike I supposed is talking about bottom-up scheduling in order to strictly implement the use of FS relationship. Meaning, he has to know the matters (beforehand) as detailed as he can in order to develop a Level 4 schedule. Well, thats because he is a Delay Analyst, which I supposed will more likely to come in during the middle stage (with substantial details), or where uncontrollable problems arises with the project because of the developed details and its integration.
Mike, how about Top-down Scheduling? How can you strictly implement FS relationships? Considering every situation (including access rights - when working on a multi-user environment).
cheers!
Thanks for all your replies, very helpful and very much appreciated!
Keep up the good work
John
Level 4.
This is where I start on any programme.
When the first set of level 4 tasks are in place for for summarising they are converted to level 3.
If there is a lot of repetition at level then they are copy / paste until level 2 is reached.
leve 1 is when all level 2 sections are complete.
Leve 5 is a sub section of level 4.
For instance an 8 storey insitu column - flatslab superstructure takes 20 minutes from level 4 to level 2 using about 90 tasks.
Best regards
Mike Testro
I believe this is where your FS (finish-to-start) relationship will really work-out. At what level it can be used accordingly and effectively? I dont believe it will work out in level one schedule.
cheers!
Gary France of the PEO has written a definitive standard on programme levels.
Go to
http://www.planningengineers.org/publications/papers.aspx#cat2
And scroll down the list of paperes to "Standards of Levels etc ..." and download the PDF.
Best regards
Mike Testro
Level 1 - I treat as milestones + major activities only
Level 2 - Summary level schedule - usually enough to identify the critical path & long lead items
Level 3 - Project master schedule - identifies all activities - level 2 shows a summary of this level is a good way to look at - if you are really clever you can color things at this level so you can kind of get clues how things fit together in a level 2 schedule.
Level 4 - detailed schedule - usually down to shifts etc... if your doing project planning this is normally a contractor level schedule - it details all the work to be done - is to a certain extent summarised by levels above it.
Level 5 - i find rarely use in project planning but would be particularly useful for shutdown planning + maintenance planning. never had to use this level to date. usually down to
While this isnt an exact science - you will find most planners (in particular project planners) work very similarily to the above levels. some changes here and there.. but generally the same.
- Peter.
Normally planners has developed their own level system and get familiar with it. You brought this to every project you joined.
Also, Mike is right to state that sometimes level names brings confusion on the program.
From the Client side, better to include this on your PM Plan or project specifications requirement so you would be able to impose your way to the Contractors.
Cheers,
R. catalan
Cheers,
Omar Grant
Go to Planning Engineers Organisation
Google PEO
They have had a good try at setting out what Levels mean.
I started to use the definitions in my programmes but contractors and clients got confused when they thought level 4 was the storey height.
I have now developed my own system
1. Project
2. Section / Zone
3. Task Summary
4. Task
Task being 1 trade working in 1 area on its own - any duration more than 10 days is too long.
Task Summary being all the tasks needed to complete a section of work.
Section - Zone being all the task summaries that are in the Section / Zone
Project - All sections / zones summarised.
This is called "bottom up Planning" qand I reccomend this way of setting up a programme.
Best Regards
Mike Testro
PP Market Place:
Safran Project: We want to build software that solves real problems, allow people to work more productive and happier. (Software) Read more...

Replies