Piping Tie In Lead Times

Member for

19 years 6 months
Permalink

Hay Andrew



If you are looking for the Procurement of Materials, then you should take into account what time it takes for the following...

1.Preparation & finalisation of Material Requisitions,

2.Issue it to Vendors for quotations

3.Technical bid evaluation is to be done

4.Prepare the purchase order ...

Also you ve to consider the lead time required ...



it would be better if you talk with your procurement guy..or directly with the Subcontractor regarding all these....



hope this clears ur doubts...



& for your info I am not a procurement guy...


Member for

18 years 6 months
Permalink

Andrew,



How big are the pipes? This is a prime consideration especially for large diameter. I suggest to get a the schedule of your subcon and check if their time-frame fits your master schedule. If not go back to them and compress.



Hernan

Member for

19 years 1 month
Permalink

i’m afraid i’m not qualified to answer that. please refer to the one incharge of the procurement

Member for

18 years 7 months
Permalink

The fabrication will take no time...Just to weld a valve onto a piece of CS pipe...I’m more concerned with how long it will take to procure the materials...They are doing the procurement, just wanna make sure I fit it into the schedule properly as to when I should get them the piping tie-in package...

Member for

18 years 7 months
Permalink

Sorry about that, the piping is Carbon Steel...Very short lead times...What they are fabricating in the field would be a valve onto the T, or a putting a blind on the flange, so they can still run the process unit, then we will come in later on and install the new line to the existing...



So baically how long to procure and fabricate the "tie-in", currently I am allowing 12 weeks...

Member for

18 years 7 months
Permalink

The sub is only responsible for the tie-in, not actually connecting up the pipe to the tie-in...They are only basically putting T’s and elbows w/ valves...Then we are coming through after and fitting up the pipes...



My question would be better asked if I said how soon should I get the sub the tie-in package, to allow them to procure the CS valves, T’s, elbows...And have time to field fab them...CS has a pretty short lead time..

Member for

19 years 1 month
Permalink

Andrew Sherwood wrote:"My question is how soon before the actual installation should the tie in package be RAS for the sub (Tie-In package contains the weld procedures, P&ID’s, ISO’s, Photo’s of the Tie in Location, etc...)"



that will depend on the length of your piping and the locations of the tie-ins. I suppose it will go at the same time, if your pipes are ready, so are the tie-ins.