I am working in Karachi, Pakistan as a planning engineer for multi-story building project having 12 buildings each ground + 17 floors. The project is being awarded to top contractors of the country :
1. Associated Constructors Pvt. Ltd
2. Habib Rafiq Pvt. Ltd.
3. Builders Associates Pvt. LTd.
The floor cycle we have achieved so far, varies from 15 days to 22 days depending on the formwork system. Completion period of one floor is about 26 days. Structure work is in progress.
If you need any more information, please don’t hesitate to send e-mail to kashifstudy@yaoo.com
Thanks,
Kashif Farooqui
Planning Engineer
Member for
20 years 6 months
Member for20 years6 months
Submitted by Zhang Haixiang on Wed, 2005-09-07 00:59
Member for
21 years 6 monthsRE: Planning in Pakistan
Top listed contractors in pakistan
1)Descon Engineering limited
2)Habib Rafique
3)SKB
4)Sachel
5)Chinese............compnies i.e on mangla etc
6)Italian...........compies...i.e impregilio...
If u need some, u can ask me..
regards,
Shahab
Member for
21 years 9 monthsRE: Planning in Pakistan
I am working in Karachi, Pakistan as a planning engineer for multi-story building project having 12 buildings each ground + 17 floors. The project is being awarded to top contractors of the country :
1. Associated Constructors Pvt. Ltd
2. Habib Rafiq Pvt. Ltd.
3. Builders Associates Pvt. LTd.
The floor cycle we have achieved so far, varies from 15 days to 22 days depending on the formwork system. Completion period of one floor is about 26 days. Structure work is in progress.
If you need any more information, please don’t hesitate to send e-mail to kashifstudy@yaoo.com
Thanks,
Kashif Farooqui
Planning Engineer
Member for
20 years 6 monthsRE: Planning in Pakistan
i have no idea of this kind of buiding.
I think you can find good contractor there.
We have built a nuclear powerplant there, most of the civil works are done by local contractor.
Member for
20 years 2 monthsRE: Planning in Pakistan
Thanks Shahzad,
Unfortunately it is not that job in Islamabad but rather Karachi.
Jason
Member for
22 years 3 monthsRE: Planning in Pakistan
I think you are coming from Al Habtoor Group for their project in Islamabad.
There are different contractors in Pakistan who have ability to complete such type of structures but limited to 15~25 stories at best.
Completion period for one Floor is from 20~30 days.