If you are into trouble probably original schedule was no good. At times in order to recover you will have to re-schedule your plans with completely new logic. Let the team that will be responsible to implement it be free to make the necessary adjustments, if major surgery is required then let it be.
The fixation with Baseline Schedule some owners and delay analysts have can do more harm than good to the scheduling and managing of the job.
it,s available to fix actual
it,s available to fix actual dates as baseline from Global Changes then add Remaining Works but i want to get the best detailed procedure to do that?
If you are into trouble
If you are into trouble probably original schedule was no good. At times in order to recover you will have to re-schedule your plans with completely new logic. Let the team that will be responsible to implement it be free to make the necessary adjustments, if major surgery is required then let it be.
The fixation with Baseline Schedule some owners and delay analysts have can do more harm than good to the scheduling and managing of the job.