Recovery Schedule

2 replies [Last post]
Amro Ahmed
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 107

Dear All,

What the best method to issue Recovery Schedule   using baseline and update are already exist in step

Replies

Amro Ahmed
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 107

it,s available to  fix actual dates as baseline from Global Changes then add Remaining Works but i want to get the best detailed procedure to do that?

Rafael Davila
User offline. Last seen 2 hours 59 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

If you are into trouble probably original schedule was no good. At times in order to recover you will have to re-schedule your plans with completely new logic. Let the team that will be responsible to implement it be free to make the necessary adjustments, if major surgery is required then let it be.

The fixation with Baseline Schedule some owners and delay analysts have can do more harm than good to the scheduling and managing of the job.