S-curve and Weightings

1 reply [Last post]
Joshua Juaneza
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 11
I am trying to refresh my memory about planning, since I underwent a surgery. I can’t remember now how to create an S-curve using Primavera Project Planner ver. 3.1 or P3. Also, I have trouble recalling how to use WEIGHTING in loading for resources. Could somebody help me recall everything?...PLS. I BADLY NEED TO RECALL..because I need to go back to my previous job as Planner. Thanks in advance

Replies

Jawad Al-Nimri
User offline. Last seen 12 years 5 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 39
Groups: None
Dear,

you must load resources & costs to your schedule, giving them the unite rates, then you will go to veiw / resource profile, choose all then display costs. it is that simple. i think you meant something else, right???