WBS Summary activity VS LOE activity

No replies
Abbas Rajabpour
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 7 Oct 2022
Posts: 22
Groups: None

Hi,

There are sometimes in our projects that we use LOE to put the cost for a WBS with some activities ( Because of an internal agreement)

I wanted to know which one is better and why? ( LOE or WBS Summary)

Santosh Bhat
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

WBS Summaries will capture the start and end dates from all activities within the WBS Group. LoE (hammocks) allow you to select which activities drive the start and end dates, and they do not need to be within the same WBS group either.