when I import updated data I lose the WBS data, perhaps there should be no format when importing?

Member for

13 years 4 months

Hey John,

 

Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?

Member for

13 years 4 months

Hey John,

 

Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?

Member for

13 years 4 months

Hey John,

 

Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?

Member for

20 years 6 months

John,

WBS has to be imported, or else all activities are by default dropped into the very top level node.