Remaining Finish Date cannot be earlier than Remaining Start Date

Member for

13 years 4 months

Thanks everyone.

Member for

19 years

Hi Rod,

Just in case it happened to you again next time, just show the time because it is the always the culprit. By defaul P6 always use 12:00AM which is earlier than your calendar working hours and causing this error. It happened only when your activity was already started or tick the Started status.

Member for

13 years 4 months

Ha! Got it, it was a Resource problem! Removed the Resource and I was allowed to reset the date, hmmm, maybe I could have just reset the Labour Units?

 

Anyway, Removed then reassigned the resource. Thanks for helping me work this out, as soon as I posted my original question, I thought, Oohhh, Hang on,.....