Copy of activity - activity ID is not following the default settings

Member for

22 years 9 months

Pierre,

Could you give us an example of the unexpected result you've got when you copy / paste the A1000 activity?

Alexandre

Member for

8 years 8 months

Hi,

We use Primavera P6 version 17

Member for

8 years 8 months

No, that i did check. 1001 was not existing already

Member for

22 years 9 months

Pierre

Don't you have an activity ID "1001" yet? In that case, P6 will number the pasted activity "1001-1" or from the last ID in your project

Alexandre