Oracle Primavera - PM6 Member for 13 years 4 months Member for 13 years 4 months Submitted by rodneyoz on Wed, 2020-05-20 11:26 Permalink Brilliant, Yes, it was the Brilliant, Yes, it was the Timeperiods. Thanks. Rod Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2020-05-19 13:35 Permalink you have not set the hours you have not set the hours correctly or have not set the correct default calendar Member for 21 years Member for 21 years Submitted by David Kelly on Tue, 2020-05-19 13:19 Permalink Modify your calendar, and Modify your calendar, and tick the "Time periods" button. These values control the multiplier/divider for hours and days Log in or register to post comments
Member for 13 years 4 months Member for 13 years 4 months Submitted by rodneyoz on Wed, 2020-05-20 11:26 Permalink Brilliant, Yes, it was the Brilliant, Yes, it was the Timeperiods. Thanks. Rod
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Tue, 2020-05-19 13:35 Permalink you have not set the hours you have not set the hours correctly or have not set the correct default calendar
Member for 21 years Member for 21 years Submitted by David Kelly on Tue, 2020-05-19 13:19 Permalink Modify your calendar, and Modify your calendar, and tick the "Time periods" button. These values control the multiplier/divider for hours and days
Member for
13 years 4 monthsBrilliant, Yes, it was the
Brilliant, Yes, it was the Timeperiods.
Thanks.
Rod
Member for
16 years 3 monthsyou have not set the hours
you have not set the hours correctly or have not set the correct default calendar
Member for
21 yearsModify your calendar, and
Modify your calendar, and tick the "Time periods" button. These values control the multiplier/divider for hours and days