Actual Labor Units Should Not be Budgeted Labor Units If Performance is not as per baseline

Member for

5 years 6 months
Permalink

Thanks Zoltan

Member for

16 years 3 months
Permalink

open your project 

go to the PROJECTS directory 

click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked