Oracle Primavera - PM6 glad I could help glad I could help Thanks Zoltan Thanks Zoltan open your project go to the open your project go to the PROJECTS directory click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked Log in or register to post comments
open your project go to the open your project go to the PROJECTS directory click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked
glad I could help
glad I could help
Thanks Zoltan
Thanks Zoltan
open your project go to the
open your project
go to the PROJECTS directory
click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked