Curved Data Date - why? what? when? is it for?

Member for

16 years 3 months

click on the crooked progress line icon and it wil be a straigh line.

 

[[wysiwyg_imageupload:7096:]]

 

Member for

12 years 5 months

OK, not that hard to solve, it is the "Progress Line" which overlays the Data Date line.  Obviously I didn't use it much prior.  I kind of assumed it was something like that but here is a confusing aspect.  I don't have a Baseline attached to that schedule - so how can it be telling me how ahead or behind the dates are - meaning how can the line be crooked?