Critical bars Display before Baseline

3 replies [Last post]
Muhammad Saqib
User offline. Last seen 4 years 31 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Hi Everybody,

Please clarify this

Why my some actvities are showing Red in Gantt Chart even i didn't make the baseline and not entered the project must by Finish Date.

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you must have an end date either on the last activity or project must finish by adte 

Muhammad Saqib
User offline. Last seen 4 years 31 weeks ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

I have selected the Longest path option but not given the project finish date. Then why it shows some activites in red bar

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that depends on how you have your critical path defined it can be zero days total float or longest path

if you have it set to zero days. If you do not set a project must finish by date then the late dates will match the early dates and the float will ALWAYS be zero