Project status / % complete

Member for

16 years 3 months

you can change the original duration but once the activity begins it is best to put in remaining duration no matter how long the original duraiton duration was. If you do this you will lose the original intent. It might be best to finnd out why the original durations are not accurate. If you see a trend developing then go ahead and revised the original durations of the activities not started. If the original durations are not being held to due to a delay then thats another story. 

Member for

6 years 11 months

Hi Zoltan

Thaks for another explanation and advice.

Regards,

Carlos Santos

Member for

6 years 11 months

Hi Zoltan

Straight Math, that is a valid point of view and also how P6 works.

Another point of view is:

The original duration that we estimated is nothing more as a prediction.

When we perform the project and track it we could realize the duration of an activity could be different than original, our prediction were wrong.

So we "inform" P6 we need more time to perform the activity, example: remaining 4 days.

Automaticaly P6 calculate all values accordingly the original duration.

Should we change the original duration???

Regards,

Carlos

Member for

16 years 3 months

you have 10 days and the remaining is 4 days that means of the 10 days that you completed 6 days of work

therefore 6/10=.60 or 60% 

straight math

Member for

20 years 6 months

that's how P6 calculate it. something like bugdeted duration for work performed.

duration % complete= (OD-RD)/OD