One Resource Across Multiple Departments

2 replies [Last post]
Matthew Walker
User offline. Last seen 4 years 43 weeks ago. Offline
Joined: 26 Jun 2019
Posts: 2
Groups: None

I just started with an engineering company that needs some real help with their scheduling system.

The first priority is being able to produce a staffing plan from the schedule. The issue I'm running into is that our Instrumentation and Electrical group shares resources. Joe Schmo could work 10 hours on Electrical work and 30 hours in Instrumentation work. I need a way to track Joe Schmo's total hours but also separate out his work in the two different departments.

What is the best way to do this within P6?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make it a global resource and then also use roles so you can assign Joe Shmoe. 

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

For example, Create a Resource Calendar setting the Time 8am-6pm every M-W-F (Department 1), 8am-1pm every T-Th (Department 2).