EPPM Schedule Check

Member for

16 years 3 months

Joao

xertool kit is good but it costs money to buy. A free tool to use to perform the DCAM 14 point schedule analysis a free excel based is xer- reader tool here is the link. Another nice tool in there is the ability to print the calendars something that is missing from P6

https://github.com/djouallah/xer-reader

 

Member for

20 years 6 months

Craig, ok Understood, I've not used EPPM/ P6 Web much hence the confusion. Thank you for clarifying.

Member for

11 years 6 months

The ''Check Schedule'' functions exists for EPPM versions only and runs precisely the DCMA 14 assessment. So you check with your IT, why you dont have t.

However and whenever I do not have access to the EPPM version, I like to use an external tool called Schedule Toolkit: https://xertoolkit.com/

Takes me less that one minute to have all reports in my hands and it is easy to ready / share.

Member for

16 years 3 months

I think you are talking about Check Project Integrity

in version 6.2 it is under the tools option

Member for

6 years 4 months

Hi Santosh, thanks for your reply. However, it is not that feature that I was referring too. As I said it was a feature named 'Check Schedule'. I have provided a link below to a guide to using the feature back in Primavera v8.2. 

http://www.projwebsite.com/publications/TechTip_Running_the_Check_Schedule_Feature_with_P6_EPPM.pdf

I have since spoken to someone else who said that the feature does still exist so I will have to wait and see once IT get my laptop working! 

 

Thanks

Member for

20 years 6 months

Craig, I think you're referring to the schedule comparison feature, that let you compare the differences between two schedules, P6 has never had an inbuilt schedule checking tool like DCMA checklists etc.

You can always run counts of activities in P6 as I've shown in my article here: http://www.austprojplan.com.au/using-p6-activity-counts-to-review-your-schedule/