Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Day Rate for Resources

2 replies [Last post]
Krishna Chattoo
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 20 Jun 2019
Posts: 2
Groups: None

Is there a way to enter a day rate rather than an hourly rate in Primavera?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the resource the default units/time is day

Raymund de Laza
User offline. Last seen 32 weeks 22 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Set the Unit of Time in Day for Unit Format and Duration Format in the User Preferences under Time Units Tab