Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-05-30 14:12 Permalink is your schedule resource is your schedule resource loaded ? what are you using as your measuring stick > Member for 21 years Member for 21 years Submitted by David Kelly on Thu, 2019-05-30 10:00 Permalink Katia,SChedule % complete is Katia, SChedule % complete is correct It comes from the baseline copy defined as the "Project" baseline SChedule % complete shown on summary (eg WBS) bands are waited BY COST this is very important to understand Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-05-30 14:12 Permalink is your schedule resource is your schedule resource loaded ? what are you using as your measuring stick >
Member for 21 years Member for 21 years Submitted by David Kelly on Thu, 2019-05-30 10:00 Permalink Katia,SChedule % complete is Katia, SChedule % complete is correct It comes from the baseline copy defined as the "Project" baseline SChedule % complete shown on summary (eg WBS) bands are waited BY COST this is very important to understand
Member for
16 years 3 monthsis your schedule resource
is your schedule resource loaded ? what are you using as your measuring stick >
Member for
21 yearsKatia,SChedule % complete is
Katia,
SChedule % complete is correct
It comes from the baseline copy defined as the "Project" baseline
SChedule % complete shown on summary (eg WBS) bands are waited BY COST this is very important to understand