% Complete calculated from Baseline

Member for

16 years 3 months

is your schedule resource loaded ? what are you using as your measuring stick >

Member for

21 years

Katia,

SChedule % complete is correct

It comes from the baseline copy defined as the "Project" baseline

SChedule % complete shown on summary (eg WBS) bands are waited BY COST this is very important to understand