Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

% Complete calculated from Baseline

2 replies [Last post]
Katia Popova
User offline. Last seen 4 years 45 weeks ago. Offline
Joined: 29 May 2019
Posts: 3
Groups: None

Hi there!

I am fairly new to Primavera, therefore the below question may seem a little strange to some of the pros here.

In the programme update for the client, I've been asked by a colleague to calcualte % complete that we should be on as of Data Date used for the current reporting period. I normally use % Schedule Complete to show the % complete that we should be on now. (I hope this is the right way of doing it!)
If this is the correct way of identify the % Complete we should be as of a specific Data Date, then which Baseline would this be calculated against - Project BL, Primary BL..etc? What if I have few BL assiged, which one will be picked up?

I apprecate your help!

Katia

Replies

Zoltan Palffy
User offline. Last seen 7 weeks 18 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

is your schedule resource loaded ? what are you using as your measuring stick >

David Kelly
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Katia,

SChedule % complete is correct

It comes from the baseline copy defined as the "Project" baseline

SChedule % complete shown on summary (eg WBS) bands are waited BY COST this is very important to understand