Help- Copying P6 activities to MSP

Member for

24 years 6 months

You may paste into Microsoft Project the Outline Level as a number to set the Outline of activities as you paste them in.

Paul E Harris

Eastwood Harris Pty Ltd

www.eh.com.au

Project Control Consultants and Planning and scheduling software book and training manual publishers

Member for

16 years 3 months

you can not do that 

the resource that was added and assigned at the time time they were input remain in effect

solution create another resource

copy both to excel and populate the new resocue with the values on the old resource

import the resources then delete the resource no longer needed. 

Member for

6 years 5 months

Hello dear,

i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please 

 

Regards 

Irfan Ali 

irfanali.pe12@gmail.com

Member for

6 years 5 months

Hello dear,

i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please 

 

Regards 

Irfan Ali 

irfanali.pe12@gmail.com

Member for

6 years 9 months

extremely sorry for the mutliple posts. 

Cant figure out how to delete the repeated posts