i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please
i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please
Member for
24 years 6 monthsYou may paste into Microsoft
You may paste into Microsoft Project the Outline Level as a number to set the Outline of activities as you paste them in.
Paul E Harris
Eastwood Harris Pty Ltd
www.eh.com.au
Project Control Consultants and Planning and scheduling software book and training manual publishers
Member for
16 years 3 monthsyou can not do that the
you can not do that
the resource that was added and assigned at the time time they were input remain in effect
solution create another resource
copy both to excel and populate the new resocue with the values on the old resource
import the resources then delete the resource no longer needed.
Member for
6 years 5 monthsHello dear,i need help
Hello dear,
i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please
Regards
Irfan Ali
irfanali.pe12@gmail.com
Member for
6 years 5 monthsHello dear,i need help
Hello dear,
i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please
Regards
Irfan Ali
irfanali.pe12@gmail.com
Member for
6 years 9 monthsextremely sorry for the
extremely sorry for the mutliple posts.
Cant figure out how to delete the repeated posts