Problem importing activities from excel

3 replies [Last post]
Alexander Macintyre
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 14 Feb 2019
Posts: 4
Groups: None

Hello all,

Here is the issue im facing;

I made my activity list in excel with each WBS codes with the exact codes in Primavera. I then made one new activity in Primavera, exported the xls file, added the "Activity ID", "WBS code", "Activity name" and "Duration" of each actvity, and made sure the "Duration" was formatted to text, but when I import it I get an Error message saying';

Excel Import log started : 14-Feb-19
INFO: Importing Global Data...
INFO: Importing Project Data...
INFO: Importing:
WARNING: TASK: Failed to resolve foreign key for field WBS Code with value NEWPROJ-7.Cons.Allb.Resd.St-A.Z-01.A-A1.Sust.Cnwr. Field cleared.

It has this for what I belive to be every WBS

Then it says;

ERROR: target_start_date is null for TASK ActivityID: St-A-Z-01-A-A1-3-0, Project: NEWPROJ-7

For what I assume is every activity.

I hope you guys can help.

Thanks,

 

Alex

Replies

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

double check the wbs code 

Kirill PM
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 9 Mar 2016
Posts: 14
Groups: None

it becomes easier with additional tools:

https://youtu.be/1e-AAxCMAis

Alexander Macintyre
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 14 Feb 2019
Posts: 4
Groups: None

I found the solution!

If you schedule the project and give it a data date before importing, the activies will import sucessfully.