Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Budgeted Units in Resource Assignment

1 reply [Last post]
Suhaib Nassar
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 25 Jun 2018
Posts: 13
Groups: None

Dear all,

On what basis the Budgeted Units are calculated in the Resource Assignment? I need it to be based on the manhour, but in my Xer file it is based on something else, please chech the attached screenshots shown in the second one that the budgeted units in October was zero only, whereas it is shown in the first shot that I have 32 budgeted unit on the 9th and 10th of Oct

 

6241
pri_1.png
6242
pri_2.png

Replies

Steven Auld
User offline. Last seen 6 weeks 15 hours ago. Offline
Joined: 13 Sep 2017
Posts: 126
I’m guessing that the bottom image is looking at the remaining units.
The activity you have selected is complete, so the remaining labour units will be zero.
The 32 man hours is budgeted (originally planned) labour units (and 32 hours actual labour units).
Any activity marked as complete will have zero hours remaining labour units.
Regards,
Steven