Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cumulative S-curves:

12 replies [Last post]
David Mason
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 19 Jul 2018
Posts: 6
Groups: None

Seemingly (without defaulting to Excel) we STILL can't generate in P6 Early and Late cumulative progress curves which form a natural continuum (at the data date) from the cumulate Actual progress curve !

Or am I missing something ??

Replies

Rafael Davila
User offline. Last seen 1 hour 50 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

You replied - Thanks Rafael - we don't have these report generators..... are they options in P6 or an external package ?

  • These are options on other software, among them old P3 software, I expect similar options to be available in P6 as these reports have been required for decades.

If your software cannot generate with ease such S-Curves as it should you might try external packages sych as Project Tracker.  Based on what their brochure says I would expect Current and Baseline Early and Late S curves be available.

Project_Tracker_More_S_Curves

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

filter for what you want then selecy select view show on bottom then select activity usage profile

then right click on the lower right graph area and select activity usage profile options

from here you can select either costs or units to be diaplayed as well as the baseline and or the current schedule

 

5856
1capture.jpg

David Mason
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 19 Jul 2018
Posts: 6
Groups: None

Thanks Rafael - we don't have these report generators..... are they options in P6 or an external package ?

The only one i can dig up is teh "Resource Usage Profile Options" which allows the stacked histogram and a default overall planned curve :(

  

Rafael Davila
User offline. Last seen 1 hour 50 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

This is how ancient P3 would give you the Early and Late Cumulative "S" Curves for current plus two target/baselines.

 

SCurve01

This is how Spider Project would give you the S Early and Late Curves for current plus two baselines named baseline and compared schedules.

SCurve02

I do not use P6 but it shall be as easy as 1,2,3, so easy, no big deal.

David Mason
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 19 Jul 2018
Posts: 6
Groups: None

These are the only curves P6 offers.....

Baseline

Budgeted

Actual

Remaining Early

Remaining late

Planned Earned Value

Earned Value

Estiamte at Completion.

 

Where do you source the Baseline Early and Late from please ??

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

do you use store period performance ? if not you should 

Rafael Davila
User offline. Last seen 1 hour 50 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

As soon as there is progress and the DD is moved then for current updated schedule actual Early and actual Late S Curves will overlap to the left of DD giving you the impression it is a single line. Then after the current DD they will separate showing current plan early and late cumulative S Curves.  Try setting your diagram to show both Early and Late cumulative S Curves and nothing else.  

If you select to display remaining S Curves, only remaining values at DD will be considered and it will be 0 at DD.  It will not accumulate whatever is at the left of the DD.  Try setting your diagram to show both Early Remaining and Late Remaining cumulative S Curves and nothing else.

You can add to the diagram the original plan Early and Late S curves.

Now try showing all at the same time.

Good Luck

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

To obtain the required curve, Actual Values shall equate with Earned Values and the Remaining Values shall be the difference between At Completion and Actual Values.

David Mason
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 19 Jul 2018
Posts: 6
Groups: None

Schedule is resourced with labour units and their costs.

David Mason
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 19 Jul 2018
Posts: 6
Groups: None

Yes - that's what I want them it to do (but the remaining curves start from zero again at the data date).

If P6 could hold the Early & Late cumulative curves at the baseline - this would give an envelope between the early and late curves which the actual progress curve could be measured against. But P6 doesn't offer this yet and defaulting to Excel as usual :( 

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Early Remaining or Late Remaining Curves shall originate from the End of the Actual Values at Data Date. The Curve shall be Continues until At Completion Values.

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

progress based on what dollars, manhours or units ? What is your measuing stick ?