Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Progress monitoring

3 replies [Last post]
Gowhar Mir
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 7 May 2018
Posts: 29
Groups: None

I am working on this prog that was made by someone else. I, don't assign cost or labor units to engineering activities such as submissions and approvals of materials, drawings etc because often these  activities have a lot of float so they end up messing the percentage values (as I have noted that scheduled percentage values are calculated from early start date. Hence despite having a total positive float the project lagged behind in the percentage leading to tussle with the client). What I found in the prog I received is that cost and labor units both were assigned to activities in engineering and procurement because then only the schedule percentage and unit percentage values rolled up in the summary. Is there any other way you guys are monitoring your progress?

I am new to this field trying to learn.

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

progress would be based on what is done and what is not done. This will determine float values. 

if you are not using manhours or cost then you will have to the original time frame vs the current date vs forecated time frame 

ie

original project 1000 days

as of the current data date you are on # 500 therefore linerarly 50% of your available time frame has elasped. You should be 50% complete because 1000/500 = 50%

actual progress shows you finishing on day #1300 you are 300 days behind schedule. Data date is day #500

Therefore 1300/500   = 38% complete actual vs planned 50%

you can apply this same logic based on # of activities planned to ve completed vs # of activities actually completed

 

Gowhar Mir
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 7 May 2018
Posts: 29
Groups: None

Can you please elaborate a bit? Thanks a lot for the rest of the help.

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

by manhours and cost for physcial work