Progress monitoring

G
Gowhar Mir 👤 Member for 8 years 1 month

I am working on this prog that was made by someone else. I, don't assign cost or labor units to engineering activities such as submissions and approvals of materials, drawings etc because often these  activities have a lot of float so they end up messing the percentage values (as I have noted that scheduled percentage values are calculated from early start date. Hence despite having a total positive float the project lagged behind in the percentage leading to tussle with the client). What I found in the prog I received is that cost and labor units both were assigned to activities in engineering and procurement because then only the schedule percentage and unit percentage values rolled up in the summary. Is there any other way you guys are monitoring your progress?

I am new to this field trying to learn.

 

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

progress would be based on what is done and what is not done. This will determine float values. 

if you are not using manhours or cost then you will have to the original time frame vs the current date vs forecated time frame 

ie

original project 1000 days

as of the current data date you are on # 500 therefore linerarly 50% of your available time frame has elasped. You should be 50% complete because 1000/500 = 50%

actual progress shows you finishing on day #1300 you are 300 days behind schedule. Data date is day #500

Therefore 1300/500   = 38% complete actual vs planned 50%

you can apply this same logic based on # of activities planned to ve completed vs # of activities actually completed

 

G
Gowhar Mir 👤 Member for 8 years 1 month

Can you please elaborate a bit? Thanks a lot for the rest of the help.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts