Hide Activities in P6

Member for

16 years 3 months

"HIDING" activities or filtering activities in no way shape or form change your durations that is impossible. 

I am not sure what your are trying to dsiplay but filtering will NOT chnage any durations

Member for

20 years 6 months

I think what you're suggesting, is, that after you've applied a filter, the overall dates being displayed for your project are now different?

 

P6 only summaries to grouping bands for the activities that are being displayed. You cannot display the finish dates for activites that are not being displayed.

Member for

7 years 4 months

 

Can you post the screenshot of the filter parameter & condition you used