Roll Up Performance % Complete

1 reply [Last post]
Emma Lang
User offline. Last seen 1 week 6 days ago. Offline
Joined: 9 Aug 2016
Posts: 16
Groups: None

I have some activities with zero resources against them. Basically a manufacture line, which I put a % complete against. I would like this to roll up to the summary level. 

Is this possible to do in P6? I've tried changing the % complete type. even using a dummy resource. But it doesn't seem to roll up. 

 

Any suggestions?

Replies

Zoltan Palffy
User offline. Last seen 4 hours 8 min ago. Offline
Joined: 13 Jul 2009
Posts: 1588

because you can use either physical % complete, duration % complete or unit % complete to track your % complete you can not roll up certain % completes. This is like mixing apples, oranges and bananas. Try using actviity % complete