Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Finding Slipping and Not started activity compare to baseline filter

1 reply [Last post]
Nathan Siva
User offline. Last seen 50 weeks 5 days ago. Offline
Joined: 28 Apr 2014
Posts: 28
Groups: None

Hi All,

How to identify the not started activity and slipping or negative variance activity compared to baseline using filter.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

add a column look under duration and add Variance - BL1 Start Date