Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2016-11-28 13:08 Permalink that should work that should work Member for 9 years 2 months Member for 9 years 2 months Submitted by zahidshaikh on Thu, 2016-11-24 09:48 Permalink Budgeted Total cost goes Budgeted Total cost goes missing. I will try using the add new resource setting. Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2016-11-23 14:03 Permalink which costs are we talking which costs are we talking about budgeted, actual, actual at completion which one ? also check your filter make sure that it is set to ALL also go to Projects directory make sure you project is highlighted got to the calculations tab on the right under the Resource Assignments make sure that Add actual to remaining is checked. also during the import process make sure that in the Update Project Options that select modify under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new under the Data Type Global: make sure that the action item under resources is set to insert new Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2016-11-28 13:08 Permalink that should work that should work
Member for 9 years 2 months Member for 9 years 2 months Submitted by zahidshaikh on Thu, 2016-11-24 09:48 Permalink Budgeted Total cost goes Budgeted Total cost goes missing. I will try using the add new resource setting.
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Wed, 2016-11-23 14:03 Permalink which costs are we talking which costs are we talking about budgeted, actual, actual at completion which one ? also check your filter make sure that it is set to ALL also go to Projects directory make sure you project is highlighted got to the calculations tab on the right under the Resource Assignments make sure that Add actual to remaining is checked. also during the import process make sure that in the Update Project Options that select modify under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new under the Data Type Global: make sure that the action item under resources is set to insert new
Member for
16 years 3 monthsthat should work
that should work
Member for
9 years 2 monthsBudgeted Total cost goes
Budgeted Total cost goes missing.
I will try using the add new resource setting.
Member for
16 years 3 monthswhich costs are we talking
which costs are we talking about budgeted, actual, actual at completion which one ?
also check your filter make sure that it is set to ALL
also go to Projects directory make sure you project is highlighted
got to the calculations tab
on the right under the Resource Assignments make sure that Add actual to remaining is checked.
also during the import process make sure that in the Update Project Options that select modify
under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new
under the Data Type Global: make sure that the action item under resources is set to insert new