Cost Loaded Schedule Import Error

Member for

16 years 3 months

that should work 

Member for

9 years 2 months

Budgeted Total cost goes missing.

 

I will try using the add new resource setting.

Member for

16 years 3 months

which costs are we talking about budgeted, actual, actual at completion which one ?

also check your filter make sure that it is set to ALL

also go to Projects directory make sure you project is highlighted 

got to the calculations tab 

on the right under the Resource Assignments make sure that Add actual to remaining is checked.

also during the import process make sure that in the Update Project Options that select modify

under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new

under the Data Type Global: make sure that the action item under resources is set to insert new