Skip to main content
Website Upgrade Beta Phase - we’re working on a new look (and speed!). Help us improve PlanningPlanet.com by sharing feedback.
PPadmin@planningplanet.com
Home
Discussion forum
Wiki
Schedule Maintenance
Software Settings
Progress Update
Delay Analysis
Delay Analysis
Progress Recording
Schedule Usage
Levels of Reporting
Performance Reporting
Trend Anaysis
Progress Reporting
Schedule Impact Concepts
Communicating the Plan
Deliverables
Variance Reporting
Float Management
The Purpose of the Project Schedule
Milestone Management
Trending
Openings
Utilizing CPM Schedules to Track Resources Can Cuts Costs
Schedule Construction
Activity Codes
Defining Activity Codes in Primavera 6 R8.1
Activity Durations
Rates, Norms & Durations
Shipbuilding
Fitout & Finishes
Stone Cladding
Soft Landscaping
Wall & Ceiling Coverings
Facade Waterproofing
Asphalt Waterproofing
Bituminous Waterproofing
Bentonite Waterproofing
Epoxy Waterproofing
Doors & Window Installation
Glazing
Curtain Walling
Facade Cleaning
Cladding Restoration
Kitchen Installations
Painting & Decorations
Preparatory Works
Timber
Internally
Walls
Internally
Externally
Brickwork
Floors
Ceilings
Steel
Internally
Externally
Restoration Works
Rendering
Floor Finishes
Ceiling Finishes
Carpentry Final Fixing
Carpentry Carcassing
Carpentry & Joinery
Petrochemical Oil & Gas
Pipeline Construction
Power Generation & Nuclear
Transportation
Conveying Systems
Hoists & Cranes
Rail Grab
Crane Grab
Hydraulic Excavator
Equipment Conveying decks
Railways
Floating Track Slab
Trackwork
Transportation Power Supply
Electrical System
Cable Car
Roads & Infrastructure
Road Markings
Road Surfaces
Concrete Road surfacing
Road Basecourse
Kerbs & Paving
Tunnelling & Mining
Design Works
Drill & Blast Method
New Austrian Tunneling Method
Tunnel Boring Machines
Shield Tunnelling
Headings & Hand Tunneling
Vertical Shafts
Chemical Excavation Methods
Cone Fracture Rock Breakage
Initial Tunnel Supports
Permanent Bracings
In-Situ Tunnel Linings
Tunnel Grouting
Immersed & Sunken Tubes
Micro-Tunneling
Cut and Cover Tunnels
Tunnel Leak Repairs
Pipe & Box Jacking
Pharmaceutical
IT Engineering Projects
005 Initiate Phase
010 Analyse Phase
015 Design Phase
020 Develop Phase
025 Test Phase
030 Implement Phase
035 Support Phase
Building Services / E&M
Escalator Installation
Define First Fix
Define Second Fix
Lift Installation
Fibre Cables
Bridges
Covered Steel Footbridge
Design
Formwork & Bases
Structural Steelwork
Cable Stringing
Bridge Decking
Traffic Decking
Paintwork
Final Finishes
Bridge Items - Work Activity Base Production Rates in USA
Automotive
Defence Sector
Health & Healthcare
Water Management
Elevated Watercourse
Building & Construction
Foundation Works
Contigous Piling
Driven Piles
Mini Piling
Bored Piling
Secant Piling
Hand Dug Caissons
Underpinning
Grouting Operations
Grouting
Sheet Piling & Strutting
Strutting
Sheet Piling
Secant Piling
Barrette Piles
Diaphragm Walling
Ground Anchors
Multiple Bell Ground Anchors
Removable Ground Anchors
Slurry & Soil Mix Walls
Slurry Mix Wall
Soil Mix Walls
Preparation Works
Site Clearance
Site Clearance
Site Investigation
Instrumentation
Construction Design
Earthworks & Excavation
Spread & Leveling
Dewatering
Cofferdam Works
Dewatering
Ground Compaction
Deep Compaction
Compact & Consolidate
Hand Fill & Compact
Ground Monitoring
Basement Excavations
Excavate and Remove
Basement Excavation
Trench Excavations
Traditional mass fill foundations
Excavation Works
Material Weights
Ground Excavation
Excavate & Load
Spoil By Barge
Spoil By Conveyor
Reclamation & Filling
Excavate & Reduce Levels
Steel Strutting
Bulk Excavation
Bell Ground Anchors
Bored Piling
Building Frameworks
Metal Frameworks
Roof Structure
Timber Frameworks
Roof Structure
Timber frame superstructure
Curtain Walling
Wet Trade Finishes
Blockwork
Plastering
Rendering
Screeding
Plasterboard
Roofs & Waterproofing
Flat & Layered Roofs
Asphalt Roofs
Felt Roofs
Metal Roof Decking
Metal Decking
Lead Roofing
Copper Roofing
Zinc Roofing
Aluminium Roofing
Titanium Roofing
Metal Features
Roof Lights
Sheeted Roofs
Asbestos Roofs
Profiled Sheeting
Sheeted Roofs
Tiled Roofs
Slate Roofs
Tiled Roofs
Rainwater Works
Guttering & Pipes
Roof Insulation
Thermal & Moisture Protection
Polythene Waterproofing
P.V.C. Sheeting
Gravel Chippings
Waterproofing
Demolition & Break Out
Housing Demolitions
Breaking Out & Openings
Breaking Out
Cutting Holes
Common Brickwork
Cutting Back
Cutting Chases
Cutting Switchboxes
Concrete Related Works
Formwork
Formwork Re-Use
Waffle Flooring
Tunnel Forms
Hollorib Decking
Beam Falsework Formwork
Footing formwork
Raft formwork
Walls formwork
Staircase formwork
Ramp formwork
Shades Formwork
Formwork
Reinforcement
Reinforcement
Footing Reinforcement
Walls Reinforcement
Staircase Reinforcement
Reinforcement Ratios
Placement & Finishing
Concrete Pumping
Concrete Cycle Times
Slip Forming
Place Concrete
OFC Laying
Concrete Finishing
Pre-Cast Works
Post Tensioning Works
Post Tensioning
Mixing Concrete
Granolithic Flooring
Sand / Cement Floor Screeding
Terrazzo Flooring
Mosaic Tiles
Computer Room / Raised Floors
Wood Block Flooring
Working Platforms
Tower Cranes
Partitioning
Drainage, Manholes and Gulleys
Fencing Works
Blockwork
Decking
Rule of Thumb
Budget & Cost Loading
CBS Codes
Calendars
Constraints
Crew size and mix
EPS Codes
Estimating
Hammock Tasks
Implementing Schedules
Project Control in Construction for Mining
Common Scheduling Mistakes
Human mistakes
Logic, Leads & Lags
Finish to Start Vs Start to Finish Relations in Primavera Project Planner P6
Network Rules
OBS Codes
OBS and EPS in Primavera P6
Programme Narrative
How Lean Construction Principles and Critical Path Methods Enhance One Another
Resource Loading
Resource Levelling
Schedule Levels
WBS Structure
Planning Terms
Bar
Budget
Schedule Variance
Activity ID
Bar Chart
Calendar
Constraint
Activity Duration
Critical Path Method
Free Float
Total Float
Activity
Earned Value Analysis
Arrow Diagram Method
Precedence Diagram Method
Windows Analysis
What-If Analysis
Work Breakdown Structure
Variance
Turnaround Document
Time Now
Time Impact Analysis
Start-to-Start
Start-to-Finish
Start to Finish
Slippage
Schedule Performance Index
Retained Logic
Progress Report
Progress Override
Programme
Planning Planet
Planning
Mitigation
Master Programme
Key Performance Indicator
Hammock
Gantt Chart
Cycle Time
Baseline Management
Work Package
Baseline Schedule
Critical Activity
Critical Path
Integrated Master Schedule
Current Schedule
Schedule Update
Relationship
Linear Planning
Data Date
PERT
BCWS
ACWP
BCWP
Critical Path DRAG
Scheduling
Project Controls
Cost Engineering
Integrated Project Delivery (IPD)
Latest Start Date
Earliest Finish Date
Latest Finish Date
Progress Over-Ride
Zero Float
Professional Growth
Core Competencies
Planner Recognition
Consultado Brasileiro
Professional Development for Project Controls
6 Simple/clean ways to Stay Motivated for the PMP Exam:
Q&A from Planning Planet Experts
"Mr P6 Heavy Civils"
Promotion of activity codes in Oracle Primavera P6
Calendar for scheduling relationship lags
"Mr Risk"
Risk Registers or Schedule Analysis
Optimistic and Pessimistic Durations
Seven Signs of Incompetent Managers
Books & Book Reviews
CPM Scheduling for Construction – Best Practices and Guidelines
Understanding the Impact of Big Data Analytics on Business Performance
Software Systems
Planning Software
Artemis - 9000
Oracle - Primavera P3
Sciforma PSNext
Asta Powerproject
Critical Path DRAG
Safran Project
Safran for Microsoft Project
Safran Planner
Deltek - Open Plan
Help with Schedule Finish Dates
Setting up MultiProject Open Plan Professional
Microsoft Project
Adding Password to Microsoft Project File
Check if Project Saved as Baseline
4D CONSTRUCTION SEQUENCING WITH SYNCHRO
Activity-on-Arrow Charts from MS Project
Oracle - Primavera P6 (formerly P4/P5)
Oracle - Primavera SureTrak
Artemis - Views
Oracle - Primavera P6 Web
CCS -Candy Planning / SitePlan
Asta Powerproject Enterprise
TILOS
sure trak
DynaRoad
ADePT Design Builder
Acumen Fuse
ATC Professional
eTaskMaker
Phoenix Project Manager
Streamline communications to the Project Team
ScheduleReader™
Risk Software
Oracle - Primavera Risk Analysis (formerly Pertmaster)
Intaver Institute RiskyProject
Strategic Thought - Active Risk Manager (ARM)
Deltek - WelcomRisk
Acumen Risk
Cost Software
Deltek - COBRA
Oracle - Primavera Earned Value Management
Kildrummy - CostMANAGER
CCS - Candy - Project Control Software
EcoSys - EPC (Enterprise Planning & Controls)
Cleopatra Enterprise (by Cost Engineering)
Website Help and FAQ
Email Issues
News Issues
Forum Posting Rules & Issues
Production Rates Issues
Groups Issues
Partners Issues
Consuls Issues
Jobs Issues
Voting & Polls Issues
Team Issues
Member Profile Issues
Site Newsletters
News: Friday 6th April 2012
News: Friday 27th April 2012
Building Information Modeling
BIM Software Application
BIM Tools - ( According to Georgia Tech)
Bentley
BIM Software
BIM Explained
Best Practice & Skills
Project Life Cycle
Issue Management
Stakeholder Management
Contract Management
Termination of the Contract
Interface Management
Cost Management
Comparsion of Cost Estimating Sottware and Techniques - From Spreadsheets to Today
The Most Overlooked Total Installed Cost (TIC) Items - An Integrated Consulting Article
Earned Value Management
EVM Utilized Effectively-An Integrated Consulting Article
Risk Management
Risk Identification
Risk Quantification
Risk Response
Risk Response Control
Managing Schedule Risks
Winning Risk Management
Change Management
Claims Management
Concurrent Delay
Delay & Disruption Protocol
The ‘notices’ provision in the Contract
Ownership of Float
Procedures & Processes
Constructability
The Values of Scheduling - An Integrated Consulting Article
The Values of Scheduling - An Integrated Consulting Article
Dispute Resolution
Arbitration
Litigation
Mediation
Adjudication
Project Partnering
SHEM - Safety, Health & Environment Management
White paper on resource management
Winning Project Management
3D BIM Wiki
IFC File
Tekla 3D BIM Software
3D Objects
4D BIM Wiki
4D Focus Time
Synchro 4D/5D BIM Software
5D BIM Wiki
5D BIM
6D BIM Wiki
7D BIM Wiki
7D BIM
BIM Lobbying
BIM Specialist Registry
BIM Research
BIM Model Library
BIM Case Studies
Using Unmanned Aerial Vehicles for Automated BIM-based Construction Progress & Reporting
BIM and Project Controls
Building Information Modeling
BIM Software Application
BIM Tools - ( According to Georgia Tech)
Bentley
BIM Software
BIM Explained
Best Practice & Skills
Project Life Cycle
Issue Management
Stakeholder Management
Contract Management
Termination of the Contract
Interface Management
Cost Management
Comparsion of Cost Estimating Sottware and Techniques - From Spreadsheets to Today
The Most Overlooked Total Installed Cost (TIC) Items - An Integrated Consulting Article
Earned Value Management
EVM Utilized Effectively-An Integrated Consulting Article
Risk Management
Risk Identification
Risk Quantification
Risk Response
Risk Response Control
Managing Schedule Risks
Winning Risk Management
Change Management
Claims Management
Concurrent Delay
Delay & Disruption Protocol
The ‘notices’ provision in the Contract
Ownership of Float
Procedures & Processes
Constructability
The Values of Scheduling - An Integrated Consulting Article
The Values of Scheduling - An Integrated Consulting Article
Dispute Resolution
Arbitration
Litigation
Mediation
Adjudication
Project Partnering
SHEM - Safety, Health & Environment Management
White paper on resource management
Winning Project Management
3D BIM Wiki
IFC File
Tekla 3D BIM Software
3D Objects
4D BIM Wiki
4D Focus Time
Synchro 4D/5D BIM Software
5D BIM Wiki
5D BIM
6D BIM Wiki
7D BIM Wiki
7D BIM
BIM Lobbying
BIM Specialist Registry
BIM Research
BIM Model Library
BIM Case Studies
Using Unmanned Aerial Vehicles for Automated BIM-based Construction Progress & Reporting
BIM and Project Controls
Miscellaneous
Delay Analysis
S Curve & Progress Tracking through Excel
Benefits of the Interdependent CPM Schedule Model
Notice Provisions Protect Contractors from Risk
Lean Construction Methods & CPM Scheduling Work Together
Primavera P6 Professional R16.2
Project Management - a philosophy of Life
Asset Life Cycle Management - Operations Management Vs. Capital Project Management
Modular Construction vs Traditional Construction, a Total Cost of Ownership Comparison of Data Centre Construction
Data Mining tool and techniques in construction by Knowledge Areas, state of the art situation
Project Management: Principles, Practices & Context
Production rates
Automotive
Bridges
Building & Construction
Building Services / E&M
Defence Sector
Fitout & Finishes
Health & Healthcare
IT Engineering Projects
Petrochemical Oil & Gas
Pharmaceutical
Power Generation & Nuclear
Roads & Infrastructure
Rule of Thumb
Shipbuilding
Transportation
Tunnelling & Mining
Water Management
Jobs
Advertisers
User account menu
Log in
Headers and Footers wont print to PDF
Oracle Primavera - PM6
Log in
or
register
to post comments