Converting Activity Codes to WBS in P6

Member for

16 years 3 months

open  the excel file dictionary6s.xls 

type in the password

select update project list 

then select your project

then select GET Activity Codes

now copy these codes

now open the wbs.xls file

and type in the password

select update project list 

then select your project

then select GET WBS

now copy the codes from the other spreadsheet into the wbs spredshsheet 

now in the wbs spreadsheet select SET WBS

done

 

Member for

8 years 5 months

Someone can more detail explain for us how to use SDK to convert Activities code to WBS.

Thank you so much

p/s: Video is better :D

Member for

16 years 3 months

you install sdk then you use the excel spreadsheet. Then sdk bridges the gap or is the interface between the spreadsheet and P6.

So in the spreadsheet you can select your project and you have the get button and the set button

the get button is like export in p6 and the set button is like the import function in p6

so you use the get button to export your info from p6 change it or populate it then you select set to import it back into p6  

you can do this for several different categories. 

Member for

10 years 10 months

Thanks Zoltan,

Can you further explain how i can use that in my perticular case?

Thanks

Member for

16 years 3 months

sdk stands for software development kit this come with p6. Almost every program as a sdk that they make available to developers of other software in this case sdk will be used inconjunction with excel.