Need some advise on how to resolve the below issue. My current user profile is a superuser. We have recently migrated from P6 ver 8.4 to ver 18. We use the export / import option for updating the progress due to the L5 breakdown of activities as manual updating takes ages.
Excel Import log started : 24-May-19
INFO: Importing Global Data...
INFO: Importing Project Data...
INFO: Importing:
WARNING: TASKRSRC: Failed to resolve foreign key for field Role ID with value RIGS. Field cleared.
"followed by the message below"
ERROR: Cannot assign the same Resource: RSRC: DWN-TRD-RIGS to TASK ActivityID: T2-CR-STR-3830, Project: C1587399-45 - LIVE more than once.
Any assistance in this regard would be greatly appreciated.
Thanks! I tried to export/import without changes as you mentioned but I get the same error, changes or no changes it just "thinks" I want to add a resource. This is driving me nuts. Any other ideas?
the only thing that I can think of is that since you are chaning remaining units/time that it thinks that it is a nre resource. For a test try not changing it meaning export ti then try to re-import it leaving the remaining units/time the same. This will or will not verify my theory.
I was already only importing the Resource Assignment, so I tried using the global change to update the "Claculate costs from units" field but nothing :/
I use export/import to update many fields and never get a problem, I wonder why Primavera "thinks" I want to add an extra resource...
Rajender Koilkonda Start a
Rajender Koilkonda
Hi guys,Need some advise on
Hi guys,
Need some advise on how to resolve the below issue. My current user profile is a superuser. We have recently migrated from P6 ver 8.4 to ver 18. We use the export / import option for updating the progress due to the L5 breakdown of activities as manual updating takes ages.
Hei, Thanks! I tried to
Hei,
Thanks! I tried to export/import without changes as you mentioned but I get the same error, changes or no changes it just "thinks" I want to add a resource. This is driving me nuts. Any other ideas?
-B
the only thing that I can
the only thing that I can think of is that since you are chaning remaining units/time that it thinks that it is a nre resource. For a test try not changing it meaning export ti then try to re-import it leaving the remaining units/time the same. This will or will not verify my theory.
Hi, thanks for the reply.I
Hi, thanks for the reply.
I was already only importing the Resource Assignment, so I tried using the global change to update the "Claculate costs from units" field but nothing :/
I use export/import to update many fields and never get a problem, I wonder why Primavera "thinks" I want to add an extra resource...
Any other ideas??
-B
1. FOR THE RESOURCE manke
1. FOR THE RESOURCE manke sure that calculate cost from units is set to NO if it not then run a glocal chnage and chage it from yes to NO.
2. when you import the excel back in only selct resource ASSIGNMENTS during the import process NOT the resource.