How to display No of Days in a month in TimeScale

Member for

16 years 3 months

view timescale 

then at the bottom 

ordinal dates 

then ordinal date interval is days

Member for

9 years 4 months

Hi

 

  Currently it is displayed as  Jun 2016 , August 2016 , Septemeber 2016 and so on