Varying resource start and end dates on activities

Member for

16 years 3 months

yes you can create resource calendars. When you go to calendars up top you have 3 choices global resource and project so select the resource calendar make sure ot assign the resource to the resource calendar

Member for

9 years 6 months

Thanks for the responses,

just one more question. Is it possible to create a calendar for each individual resource, which reflects the fact that some of them start later than others? Is this a more effective way of reflecting different start dates for resources?

The reason I don't want to keep resource dates synced with activity dates, and then change them individually is purely because in some cases resources start several weeks or even months after the activity starts........which means I'll be spending a lot of time individually levelling resources.....

Feedback is appreciated.

Member for

20 years 11 months

Hi Karim

First of all you should link activities and calculate the schedule. So all your Start/Finish dates for activities and assignments will be updated.

Secondly if you want your resource assignments to have different dates from activity you have to disconnect Drive Activity Dates Flag and then use Remaining Lag & Remaining Duration for each assignment.

[[wysiwyg_imageupload:3657:]]

This method has its own flaws - its not really easy to predict behavior of Activity dates when Resource assignment Finish goes beyond Finish Date of activity - activity Finish date will be updated regardless of Drive Activity Dates flag. 

So my advise is to keep activity and resource assignments dates synchro.

If you need more accurate representation - go with detalisation on activity level.

Regards,

Andrew

Member for

20 years 11 months

Hi Karim

First of all you should link activities and calculate the schedule. So all your Start/Finish dates for activities and assignments will be updated.

Secondly if you want your resource assignments to have different dates from activity you have to disconnect Drive Activity Dates Flag and then use Remaining Lag & Remaining Duration for each assignment.

[[wysiwyg_imageupload:3657:]]

This method has its own flaws - its not really easy to predict behavior of Activity dates when Resource assignment Finish goes beyond Finish Date of activity - activity Finish date will be updated regardless of Drive Activity Dates flag. 

So my advise is to keep activity and resource assignments dates synchro.

If you need more accurate representation - go with detalisation on activity level.

Regards,

Andrew

Member for

16 years 3 months

why not link the activities recalculate then schedule the project and then check how the resources are being spread over the sanctities. 

 

you do not UPDATE the start date unless it is an ACTUAL date