How to jump to a date in P6

Member for

9 years 6 months
Permalink

If you want to jump to the bar in the Gantt put your mouse next to the activity on Gantt and double click The timescale will jump to the bar.

Member for

16 years 3 months
Permalink

then add the start date to the front of the bar and the finish date to the end of the bar 

Member for

9 years 7 months
Permalink

Thanks for the response. But with this method you can jump to activity not in Gant Chart. I want to jump in Gant Chart like waht we have in MSP.thanks,

Member for

21 years 9 months
Permalink

Ehsan,Enable Activity Details form and go to the Relationship tab. Select the activity you want to "jump to" and click on the GoTo button.=jerome