Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to jump to a date in P6

5 replies [Last post]
Ehsan P
User offline. Last seen 7 years 52 weeks ago. Offline
Joined: 23 Mar 2016
Posts: 8
Groups: None

Hi everyone,

We know there is a tab in MSP to jump to a date or activity. Do we have the same in P6 as well? appreciated your responses in advance.

Replies

Helen Ward
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 20 Apr 2016
Posts: 6
Groups: None
If you want to jump to the bar in the Gantt put your mouse next to the activity on Gantt and double click The timescale will jump to the bar.
Zoltan Palffy
User offline. Last seen 3 days 3 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

then add the start date to the front of the bar and the finish date to the end of the bar 

Ehsan P
User offline. Last seen 7 years 52 weeks ago. Offline
Joined: 23 Mar 2016
Posts: 8
Groups: None

Thanks for the response. But with this method you can jump to activity not in Gant Chart. I want to jump in Gant Chart like waht we have in MSP.

thanks,

Zoltan Palffy
User offline. Last seen 3 days 3 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can always use the control-F find function

Jerome Odeh
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 19 Jan 2004
Posts: 102

Ehsan,

Enable Activity Details form and go to the Relationship tab. Select the activity you want to "jump to" and click on the GoTo button.

=jerome